Qwestrum Engineering360 · Industrial & Production · Production Planning & Control
MRP and Capacity Planning
MRP converts master schedule into time-phased component orders and checks capacity feasibility.
Exam tip: keep SI units consistent end-to-end, write the governing relation symbolically before substituting, and sanity-check magnitude and sign.
Key formulas & points
Skim these first — then read the full notes below.
- BOM explosion drives dependent demand
- MPS master schedule for end items
- RCCP rough-cut capacity check on MPS
Topic details
Introduction
Groover and Chase both present MRP as a logic engine: right part, right quantity, right time. Capacity planning prevents computationally feasible plans from becoming shop-floor impossible.
Key relations & formulas
Formulas (Indian textbook notation)
Formulas (Indian textbook notation)
Formulas (Indian textbook notation)
Notation and sign conventions
Relation 1 —
Formulas (Indian textbook notation)
Write this relation with symbols exactly as in Martand Telsang Ppc — Standard reference before substituting numbers. Examiners award partial marks for a correct setup even when arithmetic slips.
Relation 2 —
Formulas (Indian textbook notation)
Write this relation with symbols exactly as in Martand Telsang Ppc — Standard reference before substituting numbers. Examiners award partial marks for a correct setup even when arithmetic slips.
Relation 3 —
Formulas (Indian textbook notation)
Write this relation with symbols exactly as in Martand Telsang Ppc — Standard reference before substituting numbers. Examiners award partial marks for a correct setup even when arithmetic slips.
Concept in depth
The MPS drives BOM explosion to generate gross requirements at each level. Inventory records and scheduled receipts produce net requirements, then planned order releases are time-shifted by lead times. RCCP and CRP verify whether work centers can execute the plan.
Assumptions and validity limits
State assumptions explicitly before using any relation for mrp and capacity planning — steady state, uniform properties, linear elastic material, ideal gas, incompressible flow, etc., as applicable.
Wrong assumptions invalidate the entire solution even when the formula is correct. In Production Planning viva and GATE descriptive questions, listing valid assumptions often earns separate marks.
Step-by-step problem approach
1. Read the question and list given data with SI units (common in Production Planning papers).
2. Draw a neat labelled diagram where applicable — examiners in Indian universities award diagram marks even when arithmetic slips.
3. Identify which relation from this topic applies to mrp and capacity planning.
4. Use equation 1:
5. Use equation 2:
6. Substitute values, compute, and verify units and sign (direction).
7. State conclusion in one line — e.g. safe/unsafe, stable/unstable, feasible/infeasible.
2. Draw a neat labelled diagram where applicable — examiners in Indian universities award diagram marks even when arithmetic slips.
3. Identify which relation from this topic applies to mrp and capacity planning.
4. Use equation 1:
.
5. Use equation 2:
.
6. Substitute values, compute, and verify units and sign (direction).
7. State conclusion in one line — e.g. safe/unsafe, stable/unstable, feasible/infeasible.
Applications & exam relevance
MRP and Capacity Planning appears in manufacturing plants. In Indian industrial curricula this topic is tested because it connects theory to MRP, scheduling, and capacity.
GATE and semester exams often combine mrp and capacity planning with earlier units — revise prerequisites before attempting mixed problems.
Industry interview panels sometimes ask: "Where did you use mrp and capacity planning?" — answer with a lab, mini-project, or plant visit example if possible.
Common mistakes in exams
Students frequently ignore lot-sizing rules and release orders in need week instead of lead-time-offset week. Another common error is sign mistakes in net requirement calculation.
Quick revision checklist
Before attempting mrp and capacity planning problems, confirm you can:
1. BOM explosion drives dependent demand
2. MPS master schedule for end items
3. RCCP rough-cut capacity check on MPS
2. MPS master schedule for end items
3. RCCP rough-cut capacity check on MPS
Revise the solved examples in Martand Telsang Ppc — Standard reference and one previous-year GATE or university paper for this unit.
Worked examples
Try the problem first — open the solution when you are ready to check.
Net requirement computation
Problem
For week 5, gross requirement is 300, on-hand is 70, scheduled receipt is 80. Find net requirement.
Solution
Net requirement = 300 - 70 - 80 = 150 units. If lead time is 2 weeks, planned order release must be in week 3.
Conceptual check — MRP and Capacity Planning
Problem
In a Production Planning semester or GATE paper you are asked: "State the main assumption, the governing relation, and one practical consequence of mrp and capacity planning." What should a complete answer include?
📖 Standard books (India)
Martand Telsang Ppc — Standard reference
Read: Syllabus unit
Referenced in Indian B.Tech syllabus
Explore related topics
See real industrial & production careers
After exams and interviews, see how engineers actually built careers — milestones and decisions from people in the field.